Topic
Police Headquarters
The city is reviewing where to build a new police headquarters, evaluating candidate sites meeting by meeting. No final site has been selected. Civic Center Park is publicly favored by two of the seven councilmembers, and raises an unresolved question about the City Charter.
Updated as new information is verified — check back often.
Current Status — under active review
Site selection is under active review, evaluated meeting by meeting · Santa Barbara Drive taken up July 21 · 12 Corporate Plaza taken up September 2 · Civic Center Park publicly favored by 2 of 7 councilmembers
Civic Center Park is publicly favored by Councilmembers Noah Blom and Erik Weigand — two of the seven votes needed for a Council majority. STATEDon-record statements, Voice of OC [14]
Total confirmed public spending authorized so far: approximately $1,524,410 (potential contract ceiling of ~$13,121,150 if all future phases are authorized). CONFIRMEDCity Council Staff Report, July 28, 2026, Agenda Item Nos. 18, 19, 20 [19]
Most recent action: on September 2, 2026, the Advisory Committee held its third meeting; staff presented 12 Corporate Plaza site concepts (~$250 million including land) and a substation analysis; the Committee took no vote and made no recommendation on either item. CONFIRMEDAdvisory Committee meeting recording, September 2, 2026 [30]
Quick answers
Advisory Committee voted to stop studying the current 870 Santa Barbara Drive site
At its July 21, 2026 meeting, the Police Headquarters Advisory Committee voted 5-0 to recommend that the City Council cease expending further staff time and resources studying the 870 Santa Barbara Drive site. Vice Chair Noah Blom made the motion; Councilmember Michelle Barto seconded it. Chair Sara Weber clarified the motion was to stop spending resources at this time, not to permanently foreclose future consideration of the site. CONFIRMEDAdvisory Committee meeting minutes, July 21, 2026 (Attachment A, Sept 2, 2026 agenda packet) [21]
The committee cited operational constraints identified in prior council review. The motion means the three Santa Barbara Drive rebuild and renovation options shown in the site comparison below are no longer under active study by the committee.
This item was previewed in the City's “From City Hall to You” newsletter, received and published by Stu News Newport on July 17, 2026. REPORTEDCity newsletter content as carried by Stu News Newport, July 17, 2026[16]
⚠ DISCREPANCY Two checkable records conflict on whether a sale of the Santa Barbara Drive property has been discussed.
- Handwritten notes from the November 18, 2025 Ad Hoc Committee meeting, authored by James Houlihan, Deputy Public Works Director/City Engineer, show a sale and lease-back of the Santa Barbara Drive property to The Irvine Company being discussed. CONFIRMEDPublic Records Act-released document supplied by Keith Curry[28] CONFIRMEDCity of Newport Beach official Staff Directory[31]
- The City's August 3, 2026 letter to OCTA states that the City Council “has not discussed” selling that property. CONFIRMEDCity correspondence, August 3, 2026[29]
This has not been independently resolved. If you can help us stay current, please let us know.
Neither of the two conflicting documents has a verified public URL, so no links are provided for them. Houlihan's title is confirmed via the City's public Staff Directory [31].
- The current Santa Barbara Drive building is 49,284 sq ft, built in 1973, and received a 2021 Facilities Condition Assessment rating of "Fair."
- Since the 2021 assessment, recent system failures include sewer backups, electrical/fire concerns, and a generator switchgear failure.
- The building does not meet current seismic standards for "essential" facilities (police, fire, hospitals).
- Only about 20% of the building's interior space has natural light.
- The facility was not designed for modern policing technology needs — data storage, servers, secure networks, and body-worn camera / digital evidence storage.
CONFIRMEDCity of Newport Beach — March 10, 2026 Council Planning Session, Item No. 2 (Public Works staff presentation)[13]
Site comparison — the six options staff presented to Council, with cost and timeline estimates
Current Site (Santa Barbara) — Option 1: Renovate + Expand
- Land
- None
- Construction
- $152M
- Total
- $157M–$172M
- Timeline
- ~6–7 years
- Location
- Near Civic Center
Current Site (Santa Barbara) — Option 2: New 2-Story
- Land
- None
- Construction
- $161M
- Total
- $166M–$181M
- Timeline
- ~6 years
- Location
- Near Civic Center
Current Site (Santa Barbara) — Option 3: New 3-Story
- Land
- None
- Construction
- $168M
- Total
- $173M–$188M
- Timeline
- ~6–7 years
- Location
- Near Civic Center
1201 Dove Street
- Land
- None (City-owned)
- Construction
- ~$150M (incl. demolition)
- Total
- ~$150M
- Timeline
- ~3–4 years
- Location
- Airport Area (not central; increased response times)
Private Land Near Civic Center
- Land
- $80M–$90M
- Construction
- ~$153M
- Total
- ~$233M–$243M
- Timeline
- ~3–4 years
- Location
- Near Civic Center
Note: the City's September 2, 2026 Advisory Committee presentation on the 12 Corporate Plaza site describes a site at Civic Center Drive and Avocado Avenue with a similar placeholder land value ($80–90 million), and staff referred back to this same March 2026 figure during that presentation. It has not been independently confirmed whether “Private Land Near Civic Center” and “12 Corporate Plaza” refer to the same site or two distinct ones — the March 10 materials do not name the site specifically. The September 2 presentation gave a total estimated cost of approximately $250 million for 12 Corporate Plaza, citing escalation to an estimated 2029 construction start not reflected in the March figures above. STATEDsite identification not confirmed; meeting figures CONFIRMED [13] [30]
Civic Center Park
- Land
- None (City-owned)
- Construction
- ~$162M (excl. mitigation)
- Total
- ~$162M
- Timeline
- ~3–4 years
- Location
- Civic Center Campus
⚠ DISCREPANCY Two City-produced documents give the Civic Center Park cost estimate as $162 million, but they do not agree on what that figure excludes. A January 31, 2026 Advisory Committee planning presentation states the $162 million design/construction estimate is “(excluding significant mitigation).” [26] A subsequent public mailer distributed by the City's PR firm states the same $162 million figure without that caveat. [27] The City's official project FAQ separately notes that “current ranges span from approximately $150 million to more than $240 million, depending on the site evaluated... additional analysis and design work will further refine the numbers,” but does not specify what the unrefined mitigation costs might add to the Civic Center Park estimate specifically. [1] This has not been independently resolved. If you can help us stay current, please let us know.
Read the documents yourself: January 31, 2026 presentation slide · City mailer
The key open question posed by staff on March 10, 2026
"Should the City continue investing in major system upgrades in a building at the end of its useful life?"
Posed verbatim by Public Works staff to the City Council at the March 10, 2026 Planning Session. CONFIRMEDMarch 10, 2026 Council Planning Session, Item No. 2[13]
The timeline: from a 1973 shared facility to a still-undecided 2026 site
- Sep 2, 2026
Third Advisory Committee meeting
The Police Headquarters Advisory Committee held its third meeting. The agenda packet included the Sierra Club letter opposing the Civic Center Park site. [24] Staff presented two site-plan concepts for 12 Corporate Plaza (a privately owned site requiring acquisition of multiple Irvine Company- and Jenkins-owned parcels), with a total estimated cost of approximately $250 million including land — an increase from the ~$162 million figure used for other sites in March, reflecting escalation to an estimated 2029 construction start. Staff also presented an analysis of police substations as an alternative to a consolidated headquarters. The Committee took no vote and made no recommendation on either item; both were received and filed. CONFIRMEDPolice Headquarters Advisory Committee meeting recording, September 2, 2026 [30]
⚠ DISCREPANCY A public commenter noted that a City handout distributed at the meeting listed the 12 Corporate Plaza cost estimate as $240 million, while the staff PowerPoint presented minutes later in the same meeting gave $250 million. Both figures are confirmed to have been presented at the meeting; the discrepancy between them has not been independently resolved. If you can help us stay current, please let us know.
CONFIRMEDAdvisory Committee meeting recording, September 2, 2026 - Jul 28, 2026
Council approves Civic Center Park consultant contracts
The City Council approved consultant contracts tied to the Civic Center Park site. The City’s own “On the Agenda” preview for the July 28, 2026 meeting confirms the three contracts — an agreement for the project’s architectural team, an environmental consultant, and a public outreach and communications consultant — were on the Council agenda. The same preview also confirms the meeting included the 1300 Dove Street Townhome Project (132-unit, for-sale residential) as a separate item. CONFIRMEDCity of Newport Beach City Manager's Office "Insider's Guide" / "On the Agenda" preview [20] Approximately $1,524,410 is currently funded and authorized to proceed: LPA, Inc. Phase 1a conceptual design ($713,080), EPD Solutions SEIR ($346,330), Westbound Communications outreach ($315,000), and an LSA Associates on-call agreement amendment for related biological survey work ($150,000). CONFIRMEDCity Council Staff Report, July 28, 2026, Agenda Item Nos. 18, 19, 20[19] The full potential contract ceiling, if all future phases are authorized, is approximately $13,121,150 — driven primarily by LPA, Inc.'s total not-to-exceed architectural contract of $12,459,820 (covering Phase 1a design through final construction documents and construction support, most of which requires separate future City Council authorization), plus EPD Solutions ($346,330) and Westbound Communications ($315,000). CONFIRMEDCity Council Staff Report, July 28, 2026, Agenda Item Nos. 18, 19, 20[19]
These two figures are not in conflict — they answer different questions. $1,524,410 is what is funded and authorized now; $13,121,150 is the total possible size of the contracts if every future phase were to be fully exercised. Councilmember Robyn Grant opposed all three of the originally reported contracts, and Councilmember Joe Stapleton joined her in opposing only the communications contract. REPORTEDLos Angeles Times/Daily Pilot report; also reported by Hoodline (AI-assisted), citing the Times [18]CONFIRMEDcontract approvals and agenda presence confirmed by City sources; vote-dissent details reported by the Los Angeles Times/Daily Pilot (also reported by Hoodline, citing the Times) - Jul 21, 2026Second meeting of the Advisory Committee, focused on evaluating rebuilding at the current Santa Barbara Drive site (per Chair Weber's direction at the July 7 meeting).CONFIRMEDofficial agenda
- Jul 7, 2026
First Advisory Committee meeting
CONFIRMEDofficial agenda First meeting of the Advisory Committee, held in the Civic Center Community Room. Unlike other recent City committees (e.g., the General Plan Advisory Committee, the Lower Castaways and Aquatic Facility Committee), this meeting was not video recorded for public posting.
REPORTEDdrawn from written meeting materials, not a recording or transcript Resident member Sandy Meadows was absent. The committee received staff briefings on the history of the City’s past police stations and the current headquarters’ operational needs. Chair Sara Weber set the July 21 meeting’s focus on evaluating rebuilding at the current Santa Barbara Drive site. Committee member Paul Watkins raised questions about financing plans and ground-lease options for the Santa Barbara and Dove Street properties, and asked that the 12 Corporate Plaza site be reconsidered. Committee member Tom Maloney recommended staff attend an International Association of Chiefs of Police training on planning, designing, and constructing police facilities. [11]CONFIRMEDmeeting occurred per agenda; discussion details are REPORTED from written materials - Jun 9, 2026
Adopted Capital Improvement Program funding
The City’s adopted Capital Improvement Program sets aside $1.5 million in the current fiscal year for further study of the Civic Center Park site, $15 million in FY2027–2028 for final design, and $146 million in FY2028–2029 for award of a construction contract. This timeline has been moved up by roughly three years compared to the prior CIP. No explanation for the acceleration has been located in the CIP documents themselves; if a source is later confirmed, this will be updated. [21] [12]CONFIRMEDCity Council Resolution No. 2026-40, adopted June 9, 2026 - Jun 1, 2026Resident-member application deadline.CONFIRMED
- May 13, 2026
Speak Up Newport forum exchange
Former Mayor Keith Curry presented a detailed case against the Civic Center Park site at a Speak Up Newport public forum. Per the Stu News Newport columnist's account, Councilmember Blom's response was reported as "Everything Keith said is wrong," with no further explanation given. Watch the full exchange: Speak Up Newport, May 13, 2026. [9] [10] This quote is sourced to a single columnist's account, not an official transcript or recording.STATEDcolumnist's account; primary event page available - May 12, 2026
Council transitions to a new Police Headquarters Advisory Committee
The City Council unanimously approved transitioning from the prior council-only Assessment Committee to a new Police Headquarters Advisory Committee: 3 councilmembers plus 4 resident members — one with construction / real estate development / architecture / land-use experience, one with real estate financing experience, and two at-large seats with no specialized requirement — to evaluate location, design, and budget and recommend back to the full council. Resident applications closed June 1, 2026, and a committee meeting was scheduled for July 21, 2026.CONFIRMEDCity Council action & resident-committee announcement, May 12, 2026 - Mar 10, 2026City Council held a study session. Council unanimously agreed the current headquarters (built 1973) needs replacing, citing plumbing, electrical, and infrastructure issues. Staff presented a cost estimate of approximately $162 million for the Civic Center sculpture garden site; no final site decision was made. Staff was directed to continue evaluation through design work, environmental review, cost analysis, and public input. CONFIRMEDCity of Newport Beach — March 10, 2026 Council Planning Session, Item No. 2 (Public Works staff presentation) [13] Civic Center Park is publicly favored by two of the seven councilmembers, Noah Blom and Erik Weigand — a majority vote would require at least two more. STATEDon-record statements, Voice of OC [14]CONFIRMEDstudy-session facts confirmed by the March 10, 2026 staff presentation; councilmember support stated to Voice of OC
- Jan–Mar 2026The council held planning sessions on police headquarters site options. Traffic, environmental review, and cost analysis were all noted as still pending.CONFIRMEDcity project page
- Oct 14, 2025
The fully public process was voted down
The City Council voted on Stapleton's September 23 proposal. Councilmember Weigand pulled the item; Councilmember Blom offered a substitute motion removing public members and creating the closed, council-only Newport Beach Police Headquarters Assessment Committee (Blom, Weber, Barto) instead. Passed 5–1: Blom, Weigand, Kleiman, Weber, Barto voting yes; Robyn Grant the sole no vote; Stapleton abstaining. The Assessment Committee subsequently met privately to discuss site options. [8] [4]CONFIRMEDLegistar staff report, October 14, 2025 (Resolution No. 2025-65) - Sep 23, 2025Then-Mayor Joe Stapleton proposed a fully public site-selection process, including making all committee meetings open to the public. [8]CONFIRMEDCity Council staff report / minutes
- Dec 2022New councilmembers (Stapleton, Weigand, Grant, Kleiman) took office; they were not involved in the Dove Street decision.CONFIRMED
- Nov 2022The City Council (Muldoon, Blom, Dixon, Avery, Duffield, Brenner, O'Neill) approved a $30.5 million purchase of 1201 Dove Street as a future police headquarters site.CONFIRMEDstaff report, Legistar
- 2013City Hall moved from its 1948 building on Newport Blvd. to the current Civic Center. The project's cost rose from $105 million to $140.2 million during construction; a later audit found potential overbilling, and the contractor returned $365,000.REPORTED
- Nov 2012Newport Beach voters approved Measure EE, amending the 2008 Charter provision to require most (rather than all) administrative offices to be located at the Civic Center parcel, alongside a number of other Charter housekeeping changes.CONFIRMEDCity Attorney's Impartial Analysis; codified Charter text
- Feb 5, 2008Newport Beach voters approved Measure B, adding a Charter provision requiring City Hall, including the City's administrative offices, to be located on the Civic Center parcel. The amendment took effect March 3, 2008.CONFIRMEDMeasure B official text; Charter amendment record
- 1973The city acquired the Santa Barbara Drive site and built a shared Police/Fire Station 3 facility there.CONFIRMED
Sources for this timeline: the Sep 23, 2025 public-process proposal and the Oct 14, 2025 vote [8] [4], the May 13, 2026 Speak Up Newport forum exchange [9] [10], the July 7, 2026 Advisory Committee meeting [11], and Resolution No. 2026-40 adopting the Capital Improvement Program funding [21] [12].
Newport Beach Police Association: publicly opposed to remodeling the current site
The Newport Beach Police Association has publicly stated that remodeling, reconstructing, or reusing the current Santa Barbara Drive site is not an option it supports. In its stated position, the Association cites the station's age — built more than five decades ago — and its inability to reliably support evidence logging, officer operations, and emergency response for a population that has roughly doubled since it was built. STATEDNewport Beach Police Association public statement[15]
The case each side has made, in their own words
For the Civic Center Park site
Councilmember Blom
In a recorded interview: "I don't want to go out for a bond measure, I don't want to put this all on taxpayers." He also described it as "the final piece to wrap up the civic center," and, addressing the loss of sculpture garden space directly: "I have a three year old daughter, we walk every park in this city and she does love the sculpture garden. But sometimes I have to weigh fiscal responsibility at the same spot. It just seems to be the most responsible way."[14]
Councilmember Weigand
In a written statement: "With two high-profile and significant incidents occurring within months of one another at Fashion Island, it became imperative to me (and others) that we must keep our department's headquarters in and around Newport Center."[14]
Councilmember Weber
Stated she wants the station to remain centrally located, and separately asked staff to look at ways to preserve the sculpture garden rather than treating the tradeoff as all-or-nothing.[14]
City staff cost comparison
Civic Center Park is estimated at roughly $162 million. Purchasing an additional nearby property instead would likely push the cost above $233 million. Rebuilding at the current Santa Barbara Drive site would nearly double the project timeline, pushing completion into the 2030s.[6]
Raising concerns about the process or site
Councilmember Stapleton
Who had proposed the fully public process that was voted down, said afterward: "I think this is going to become one of the most expensive buildings in the history of our city," while also saying of the current Advisory Committee, "I do think the committee is doing a good job now getting out in the public and this will be that first opportunity."[14]
Councilmember Grant
Was the sole vote in favor of a fully public process from the start, and has cited the risk of delays from environmental review or litigation tied to the 2007 ballot measure.
Former Mayor Keith Curry
Has publicly opposed the Civic Center Park site in a moderated public debate.
Sierra Club, Angeles Chapter (Orange County Conservation Committee)
Submitted a letter to the City Council and Advisory Committee opposing the Civic Center Park site, citing habitat fragmentation, wetlands, and an underground aquifer, and requesting a transparent comparison of alternative sites before any final decision. [20]
Resident Jim Mosher and others
Have raised questions about the Campus Drive purchase price and site-selection reasoning discussed in the Fire Station section of this site.
Advisory Committee roster, as confirmed by the City Council on June 23, 2026
Councilmembers
- Sara Weber
- Michelle Barto
- Mayor Pro Tem Noah Blom
Resident members
- Tom Maloney
- Sandy Meadows
- Bob Olson
- Paul Watkins
The City Council confirmed this roster on June 23, 2026, as the membership of the Police Headquarters Advisory Committee. CONFIRMEDCity Council action, June 23, 2026[7] The City received 31 applications for the four resident seats. CONFIRMEDCity Council staff report, June 23, 2026, Agenda Item No. 20[17]
Notes & Sources
Numbered references for the claims above. Numbering restarts on each page. How claims are labeled →
- [1]
City of Newport Beach — police headquarters project FAQ
No final site has been chosen and no traffic or environmental study has begun for any site under consideration.
- [2]
Newport Beach City Charter (codified text)
The Charter provision added by Measure B (approved February 5, 2008, effective March 3, 2008) and amended by Measure EE (approved November 2012), which requires most of the City's administrative offices to be located on the Civic Center parcel.
- [3]
City staff report / Legistar
The November 2022 council approval of the $30.5 million purchase of 1201 Dove Street.
- [4]
City of Newport Beach — Legistar staff report, October 14, 2025: "Resolution No. 2025-65: Creating the Newport Beach Police Headquarters Assessment Committee"
The October 14, 2025 formal creation of the Newport Beach Police Headquarters Assessment Committee (Blom, Weber, Barto), the vote against a fully public process, and Robyn Grant's dissent.
- [5]
Stu News Newport
Confirmation of the four resident committee members, the Rubino application question, and the noted appearances of potential conflict.
- [6]
City staff cost comparison, as reported by Voice of OC
Cost estimates: ~$162M for Civic Center Park, above $233M for an added nearby property, and a near-doubled timeline for a Santa Barbara Drive rebuild.
- [7]
City of Newport Beach — City Council action, June 23, 2026
The confirmed roster of the Police Headquarters Advisory Committee: Councilmembers Sara Weber, Michelle Barto, and Mayor Pro Tem Noah Blom; resident members Tom Maloney, Sandy Meadows, Bob Olson, and Paul Watkins.
- [8]
City of Newport Beach — Legistar staff report, October 14, 2025: "Resolution No. 2025-65: Creating the Newport Beach Police Headquarters Assessment Committee"
September 23, 2025 proposal by then-Mayor Joe Stapleton for a fully public police headquarters site-selection process, and the October 14, 2025 vote on the substitute motion creating the council-only Newport Beach Police Headquarters Assessment Committee (Blom, Weber, Barto), passed 5–1 with Grant opposed and Stapleton abstaining.
- [9]
Stu News Newport — column, May 2026
Columnist's account of the May 13, 2026 Speak Up Newport public forum, including the reported 'Everything Keith said is wrong' response attributed to Councilmember Blom.
- [10]
Speak Up Newport — event page
Primary-source record of the May 13, 2026 'New Police Station 2026' forum featuring former Mayor Keith Curry and Councilmember Noah Blom.